Construction continues on the widening of McGinnis Ferry Road between Douglas Road and Hospital Parkway, with completion estimated for spring 2028.
Forsyth County’s Nov. 23 video update features Capital Projects Director John Jefferson discussing utility relocations, ongoing construction and upcoming work along the Johns Creek–Forsyth County boundary.
The approximately 2.5-mile segment will expand the road from two lanes to four, with two lanes in each direction separated by a 20-foot raised median. Plans also include curb and gutter, a 10-foot multi-use path on the north side and a five-foot sidewalk on the south, according to the county’s project page.
The county lists an overall project cost of approximately $52.4 million, including a construction contract of about $42.4 million. Construction inspection is listed at approximately $2.53 million, with another $337,000 for design consulting during construction.
Listed construction funding contributions total approximately $44 million: $20 million from the Georgia Department of Transportation, $14.4 million from Forsyth County, $8.1 million from Johns Creek and $1.5 million from Fulton County Water & Sewer.
The county held a groundbreaking ceremony in March 2025. Its project page lists construction as beginning that May.
The Douglas Road-to-Hospital Parkway work forms the eastern phase of a broader effort to widen McGinnis Ferry Road between Ronald Reagan Boulevard and Hospital Parkway.